Table of Contents

...

Tabs in the system

In the following sections, all tabs inclusive of their actions and content are described. 

...

Reference

Description

Status
colourRed
title1

Checkbox to hand over spare time to the next activities should previous activities be finished ahead of the estimated time. 

Status
colourRed
title2

Calculate CPM computes the critical path for the current process instance.

Status
colourRed
title3

Save will preserve made changes by the user.

...

...

Gantt

The Gantt tab displays a Gantt-Chart with the duration of each activity within a process instance. In order for the Gantt-Chart to illustrate the duration, CPM must be activated and the specific duration of each activity must be provided to the process model.

...